Breakneck Pace!



Just when I thought things would start to slow down, a phone call from the Site Manager this morning tells otherwise!

  • The lock up carpenter will finish wall straightening and door fitting today
  • Pre plaster quality inspection is booked for tomorrow
  • Friday the insulation will be installed
  • Plaster delivery and installation is scheduled for next Wednesday
  • Cabinets booked for 21st December

...And with a bit of luck the fix may also start just before the Christmas break (although realistically I think this is a little too optimistic!)

Wow!  Excited is an understatement!  I'm ecstatic!

Paul on the other hand is a little daunted, as it means he only has this weekend to do his data cabling and additional internal insulation...


2 comments:

  1. How cool is that?! Yes the house goes through stages where not much happens, then it all happens and once. Great that they are trying to get so much completed before Xmas break. Hope Paul gets the cabling done in time.....no pressure there then!

    ReplyDelete
  2. OMG that is amazing. You guys will be at pci in no time... I didnt have messaging turned on when you sent me the message the other day so it has disappeared into the ether. Our build is plodding along soooo slowly... :(

    ReplyDelete